Time and Work shortcut workshops register here:

    

Time and Work Solved Problems

Difficulty Level – Medium  
  1. A can work on 1km railway track in 1 day. In how many days, will he able to complte the work on 12km railway track?
Soln: no. of days = total work / work done in 1 day Therefore, no. of days taken = 12/1 = 12 days
  1. A can complete the work in 15 days. What fraction of work will be completed in 1 day?
Soln.:   Let the total work is 1 unit. Work in 1day = total work/no. of days to complete = 1/15th of work
  1. A can do a piece of work in 3 days and B can do a piece of work in 5 days. In how many days will the work be completed if both A and B work together?
Soln.: Using formula:                   Work done by A in 1 day = 1/3 Work done by B in 1 day = 1/5 Total work done by A and B in 1 day = 1/3 + 1/5 = 8/15 Therefore, no. of days to complete work by A and B together = 1/(Total work) = 1/(8/15) = 15/8 days which is less than 3 and 5     Using shortcut/analysis/assumption                   Let us consider the total work be 15 units (LCM of 3 and 5) So work done by A in 1 day = 15/3 = 5 units Similarly work done by B in 1 day = 15/5 = 3 units So total work done by A and B in 1 day = 5 + 3 = 8 units Therefore, no. of days to complete total work i.e. 15 units = total work/work done in 1 day = 15/8 days               Note:
  1.               Work done by A and B in 1 day will always be greater than that of A and B individually
  2. No. of days taken by A and B together will always be less than that of A and B individually
  1. A can do a piece of work in 6 days, B can do a piece of work in 4 days and C can do a piece of work in 12 days. Find the no. of days to complete the work if A, B and C work together?
Soln.: Using formula:                   Work done by A in 1 day = 1/6 Work done by B in 1 day = ¼ Work done by C in 1 day = 1/12 Total work done by A, B and C in 1 day = 1/6 + ¼ + 1/12 = 12/24 = 1/2 Therefore, no. of days to complete work by A, B and C together = 1/(Total work) = 1/(1/2) = 2 days which is less than 4, 6, 12       Using shortcut/analysis/assumption                   Let us consider the total work be 24 units (LCM of 4, 6, 12) So work done by A in 1 day = 24/4 = 6 units work done by B in 1 day = 24/6 = 4 units work done by C in 1 day = 24/12 = 2 units So total work done by A, B and C in 1 day = 6 + 4 + 2 = 12 units Therefore, no. of days to complete total work i.e. 24 units = total work/work done in 1 day = 24/12 = 2 days The above Note is valid here as well.
  1. A can do a piece of work in 6 days and B can do a piece of work in 12. Find the no. of days to complete the work if A and B work alternatively?
Soln.: Using formula:                   Work done by A in 1 day = 1/6 Work done by B in 1 day = 1/12 Total work done by A and B working 1 day each = 1/6 + 1/12 = 3/12 = ¼ Therefore, 1/4th of work is done in 2days. No. of days to complete total work if A and B work alternatively = 1/((1/4)/2) = 8 days       Using shortcut/analysis/assumption                   Let us consider the total work as 12 units (LCM of 6, 12) So work done by A in 1 day = 12/6 = 2 units work done by B in 1 day = 12/12 = 1 unit Total work done by A and B working 1 day each = 2 + 1 = 3 units in 2 days Therefore, work done in 1 day = work/no. of days = 3/2 units No. of days to complete work = total work/work in 1 day = 12/(3/2) = 8 days
  1. 30 men can complete a job in 40 days. Then 25 men can complete the same job in how many days?
Soln.: As per M1D1 = M2D2 30 * 40 = 25 * x  => x = 30 * 40/25 = 48 days
  1.   30 men can complete 1500 units in 24 days working 6hrs a day. In how many days can 18 men can complete 1800 units working 8 hrs a day?
  Soln.: As per the formula  (from my earlier blog), M1D1h1/W1 = M2D2h2/W2 => 30*24*6/1500 = 18*x*8/1800 => x = 36 days
  1. A and B can do a work in 10 and 15 days respectively. Then combinedly A & B, in how many days the work will be completed?
Soln.: As per the formula  (from my earlier blog), x*y/(x + y) A and B together can complete the work in 10 * 15/(10 + 15) = 6 days
  1. A can do a work in 10 and, A and B together can do a work in 6 days. In how many days B can complete the same work?
Soln.: As per the formula  (from my earlier blog), x*y/(x – y) B alone can complete the work in 10 * 6/(10 – 6) = 15 days
  1. A is twice faster than B and B can complete in 12 days alone. Find the number of days to complete if A and B together work?
Soln.: Given B works in 12 days A is twice faster than B => A takes 2 times less time than B Therefore, A completes work in 12/2 = 6 days A and B together can complete in 12 * 6/(12 + 6) = 4 days
Join us MBA CET 2025