Answer and solution
Correct answer: C
Solution
1. Take the total work as 1.
2. Aman and Varun together finish 1/120 of the work in a day.
Varun and Sameer together finish 1/80 of the work in a day.
3. From the first condition:
4. A + V = 1/120
5. From the second condition:
6. V + S = 1/80
7. In the first arrangement, Aman works for 20 days, Varun for 120 days and Sameer for 20 days. So:
8. 20A + 120V + 20S = 1
9. Solving these three relations gives:
10. Aman's one-day work = 1/960
Varun's one-day work = 7/960
Sameer's one-day work = 5/960
11. Now consider the new arrangement. In every 6 days:
Aman works all 6 days.
Varun works on days 1, 3 and 5.
Sameer works on days 1 and 4.
12. Work done in 6 days:
13. Aman: 6/960
Varun: 21/960
Sameer: 10/960
14. Total = 37/960.
15. In 25 such cycles, or 150 days, the work completed is 925/960.
16. The remaining work is 35/960.
17. During the next five days, the work done is:
Day 151: 13/960
Day 152: 1/960
Day 153: 8/960
Day 154: 6/960
Day 155: 8/960
18. Total work in these five days = 36/960.
19. The remaining work is completed on the 155th day.
20. Answer: 155 days.
21. Precision check: by the end of day 154, 953/960 is complete. Remaining work is 7/960; on day 155 Aman and Varun work at 8/960 per day. They need 7/8 day. Exact elapsed time is 154⅞ days, so the job finishes during day 155.
Why this method works:
The six-day cycle is the least common multiple of the two attendance periods, 2 and 3. Because everyone starts on day 1, Varun’s days are 1,3,5 and Sameer’s are 1,4. Starting either schedule a day late would change the result.
Independent check and common trap:
Daily rates can be checked directly: A+V=8/960=1/120, V+S=12/960=1/80, and 20A+120V+20S=(20+840+100)/960=1. Use whole cycles first, then daily work to distinguish elapsed time from the numbered completion day.
G Strategy shortcut
Spot: Time and Work – Combined Efficiency.Apply: Use 960 work units: A, V, S rates 1,7,5. Six-day cycle 37. After 150 days 925 done; next four days 28; 7 remain on day 155 at rate 8 →154⅞ days, completion during day 155.
Check: Daily rates can be checked directly: A+V=8/960=1/120, V+S=12/960=1/80, and 20A+120V+20S=(20+840+100)/960=1. Use whole cycles first, then daily work to distinguish elapsed time from the numbered completion day.
G Strategy: Spot: Time and Work – Combined Efficiency. Apply: Use 960 work units: A, V, S rates 1,7,5. Six-day cycle 37. After 150 days 925 done; next four days 28; 7 remain on day 155 at rate 8 →154⅞ days, completion during day 155. Check: Daily rates can be checked directly: A+V=8/960=1/120, V+S=12/960=1/80, and 20A+120V+20S=(20+840+100)/960=1. Use whole cycles first, then daily work to distinguish elapsed time from the numbered completion day.