CET Time and Work Questions with Solutions – Page 7
All 45 Time and Work questions from MBA CET 2023 and 2024 and 2025 and 2026 papers. Tap Show answer, or open the detailed solution (free login). Page 7 of 10.
7 men and 5 women can complete work in 9 days
and 5 men
and 6 women can complete the same work in 12 days.
How
long will 14 women and 6 men take to complete the
same
work?
a. 9
b. 10
c. 7
d. 5
e. 8
and 5 men
and 6 women can complete the same work in 12 days.
How
long will 14 women and 6 men take to complete the
same
work?
a. 9
b. 10
c. 7
d. 5
e. 8
Answer: A. 9
Solution — first steps
A man's daily rate is 1/68 and a woman's is 1/612. Six men and fourteen women together work at 6/68 + 14/612 = 1/9 of the job per day.
The full step-by-step working opens with a free login.
Question
P can complete a work in 12 days working 8 hours
a day. Q can complete the same work in 8 days
working 10 hours a day. If both P and Q work
together, working 8 hours a day, in how many
days can they complete the same work?
a)48/7 days
b)61/11 days
c)60/11 days
d)72/11 days
e)71/11 days
P can complete a work in 12 days working 8 hours
a day. Q can complete the same work in 8 days
working 10 hours a day. If both P and Q work
together, working 8 hours a day, in how many
days can they complete the same work?
a)48/7 days
b)61/11 days
c)60/11 days
d)72/11 days
e)71/11 days
Answer: C. 60/11 days
Solution — first steps
Hourly rates are1/96 and1/80. Together they take480/11hours.
The full step-by-step working opens with a free login.
Question
If:
A can do a piece of work in 4 hours; B and C
together can do it in 3 hours, while A and C
together can do it in 2 hours. Then determine as
to how long will B alone take to do the same
work?
a)6 hours
b)4 hours
c)8 hours
d)12 hours
e)10 hours
If:
A can do a piece of work in 4 hours; B and C
together can do it in 3 hours, while A and C
together can do it in 2 hours. Then determine as
to how long will B alone take to do the same
work?
a)6 hours
b)4 hours
c)8 hours
d)12 hours
e)10 hours
Answer: D. 12 hours
Solution — first steps
A's rate1/4; A+C=1/2 implies C=1/4. B+C=1/3 implies B=1/12, so B alone needs12hours.
The full step-by-step working opens with a free login.
Question
Machine P can print one lakh books in 8 hours,
Machine Q can print the same number of books
in 10 hours while Machine R can print them in 12
hours. All the machines are started at 9 A.M.
while machine P is closed at 11 A.M. and the
remaining two machines are used to complete
the remaining work. Approximately at what time
will the work (to print one lakh books) be
finished?
a)11 PM
b)12 Noon
c)1 PM
d) 11:30 AM
e)2 PM
Machine P can print one lakh books in 8 hours,
Machine Q can print the same number of books
in 10 hours while Machine R can print them in 12
hours. All the machines are started at 9 A.M.
while machine P is closed at 11 A.M. and the
remaining two machines are used to complete
the remaining work. Approximately at what time
will the work (to print one lakh books) be
finished?
a)11 PM
b)12 Noon
c)1 PM
d) 11:30 AM
e)2 PM
Answer: C. 1 PM
Solution — first steps
Two hours of all machines complete37/60 of the job. Remaining23/60 at Q+R rate11/60 takes23/11hours, finishing about1:05pm, closest1pm.
The full step-by-step working opens with a free login.
QUESTION
DIRECTION for the question: David and Michael together can finish a job in 4 days 19 hrs 12 min. If David works at two-thirds
Michael's speed, how long does it take Michael alone to finish the same job?
A]12DAYS
B]15DAYS
C]8DAYS
D]17DAYS
E]11DAYS
DIRECTION for the question: David and Michael together can finish a job in 4 days 19 hrs 12 min. If David works at two-thirds
Michael's speed, how long does it take Michael alone to finish the same job?
A]12DAYS
B]15DAYS
C]8DAYS
D]17DAYS
E]11DAYS
Answer: C. 8DAYS
Solution — first steps
8days. If Michael's rate is m, David's is2m/3; combined5m/3.
The full step-by-step working opens with a free login.