Rates in Arithmetic Progression Question
Question 128
Three diggers dug a ditch of 324 m deep in six days working simultaneously. During one shift, the third digger digs as many metres more than the second as the second digs more than the first. The third digger’s work in 10 days is equal to the first digger’s work in 14 days. How many metres does the first digger dig per shift?
- A15 m
- B18 m
- C21 m
- D12 m
- E30 m
Solution
Rav Singh AI · online
Hi! I am Rav Singh AI. For Q128, what do you want?
Answer key & full solution as text
Answer: (A) 15 m