Time & Work Question
Question 15
VerifiedA, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began
the work together but C left 4 days before the completion of the work. In how many days was
the work completed?
A) 11 days
B) 12 days
C) 13 days
D) 14 days
E) 15 days
the work together but C left 4 days before the completion of the work. In how many days was
the work completed?
A) 11 days
B) 12 days
C) 13 days
D) 14 days
E) 15 days
- A11 days
- B12 days
- C13 days
- D14 days
- E15 days
Solution
Rav Singh AI · online
Hi! I am Rav Singh AI. For Q15, what do you want?
Answer key & full solution as text
Answer: (A) 11 days
🔓 Full solution is free for Cetking students.