Time & Work Question
Question 147
VerifiedP, Q and R together can complete a work in 40 days. P and Q together can complete the
same work in 90 days. Then R alone can complete the same work in how many days?
a. 40
b. 72
c. 84
d. 90
e. 80 Ck