6 men can do a piece of work in 12 days. How
many men are needed to do the work in 18 days.
(a) 3 men
(b) 6 men
(c) 4 men
(d) 2 men
(e)None of these
  1. 3 men
  2. 6 men
  3. 4 men
  4. 2 men
  5. None of these

Solution

Rav Singh AI · online

Hi! I am Rav Singh AI. For Q111, what do you want?
Answer key & full solution as text

Answer: (C) 4 men