Mandays Question
Question 106
VerifiedThirty men finish a job in 20 days, working 9 hours per day. At the same hourly rate per man, how many hours daily must 40 men work to finish that job in 20 days?
- A6 h 45 min
- B7 h 30 min
- C8 h 45 min
- D6 h 30 min
- E7 h 15 min
Solution
Rav Singh AI · online
Hi! I am Rav Singh AI. For Q106, what do you want?
Answer key & full solution as text
Answer: (A) 6 h 45 min
🔓 Full solution is free for Cetking students.