Wages by Work Share Question
Question 128
A can do a piece of work in 10 days, B in 15 days. They work together for 5 days, the rest of the work is finished by C in two more days. If they get Rs 3000 as wages for the whole work, what are the daily wages A, B and C respectively (in rs ? ) :
- A300,200,250
- B200,300,250
- C300,200,400
- D300,250,500
- E300,400,250
Solution
Rav Singh AI · online
Hi! I am Rav Singh AI. For Q128, what do you want?
Answer key & full solution as text
Answer: (A) 300,200,250