Men Women Efficiency Question

Question 116

5 men or 7 women can do a piece of work in 28 days. find the time required by 7 men and 5 women to complete the task?
  1. 9 days
  2. 13 days
  3. 11 days
  4. 12 days
  5. 10 days

Solution

Rav Singh AI · online

Hi! I am Rav Singh AI. For Q116, what do you want?
Answer key & full solution as text

Answer: (B) 13 days

🔓 Full solution is free for Cetking students.