Question 124
A contractor undertook to do a certain piece of work in 9 days. He employed a certain number of men, but 6 of them were absent from the very first day, and the rest could finish the work in 15 days. The number of men originally employed were:
- A12
- B15
- C18
- D20
- E24
Solution
Rav Singh AI · online
Hi! I am Rav Singh AI. For Q124, what do you want?
Answer key & full solution as text
Answer: (B) 15