Time & Work Question

Question 127

Verified
To complete a piece of work, Samir takes 6 days and Tanvir takes 8 days alone
respectively. Samir and Tanvir took Rs.2400 to do this work. When Amir joined them, the work
was done in 3 days. What amount was paid to Amir?
A. Rs. 300
B. Rs. 400
C. Rs. 800
D. Rs. 500
E. Rs. 100
  1. Rs. 300
  2. Rs. 400
  3. Rs. 800
  4. Rs. 500
  5. Rs. 100

Solution

Rav Singh AI · online

Hi! I am Rav Singh AI. For Q127, what do you want?
Answer key & full solution as text

Answer: (A) Rs. 300