Time & Work Question
Question 128
Verified. Dev completed the school project in 20 days. How many days will Arun take to
complete the same work if he is 25% more efficient than Dev?
A. 10 days
B. 12 days
C. 16 days
D. 15 days
E. 5 days
complete the same work if he is 25% more efficient than Dev?
A. 10 days
B. 12 days
C. 16 days
D. 15 days
E. 5 days
- A10 days
- B12 days
- C16 days
- D15 days
- E5 days
Solution
Rav Singh AI · online
Hi! I am Rav Singh AI. For Q128, what do you want?
Answer key & full solution as text
Answer: (C) 16 days